15A NCAC 02Q .0605 (a) The Director may:



(1) (2) (3)



FINAL ACTION ON PERMIT APPLICATIONS



issue a permit containing the conditions necessary to carry out the purposes of G.S. 143, Article 21B; rescind a permit upon request by the permittee; or deny a permit application when necessary to carry out the purposes of G.S. 143, Article 21B.



(b) The Director shall issue a permit for the construction or modification of a transportation facility subject to the rules in 15A NCAC 02D .0800 if the permit applicant submits a complete application and demonstrates to the satisfaction of the Director that the ambient air quality standard for carbon monoxide shall not be exceeded. (c) The Director shall issue a permit for a period of time necessary to complete construction, but such period shall not exceed five years. (d) The Director shall not approve a permit for a transportation facility that:



(1) (2) (3)



History Note:



interferes with the attainment or maintenance of the ambient air quality standard for carbon monoxide results in a contravention of applicable portions of the implementation plan control strategy, or is demonstrated with dispersion modeling to exceed the ambient air quality standard for carbon monoxide Authority G.S. 143-215.3(a)(1); 143-215.108; 143-215.109; Temporary Adoption Eff. March 8, 1994 for a period of 180 days or until the permanent rule becomes effective, whichever is sooner; Eff. July 1, 1994; Amended Eff. February 1, 2005.






Email us

Last Modified: Thu Apr 10 08:26:10 2008
 Visit the NCDENR web portal
Top of Page